Maintenance shutdown during December 26-30, 2024
SERC plans to have its annual power shutdown to the building during December 26-30 for repair and maintenance of various components including
-
transformers, DGs,
-
breakers, batteries and chargers in the electrical substation,
-
checking, cleaning and tightening all electrical connections of all MCCs, out-put panels, PDBs, LDBs, Distribution panels etc in each floor of the building
-
Pumps, motors, blowers alignment, strainer cleaning on the chiller lines etc.
Please note that during this shutdown, there will not be any form of UPS power (either from transformer or DG) to the building. Only raw power will be available. You may remember this activity from the earlier years. We haven’t done this shutdown over the past few years since our electrical substation was getting upgraded.
Requesting for kind cooperation and to take necessary precautions